abc corporation uses an activity-based costing system with three activity cost pools. the company has provided the following data concerning its costs and its activity-based costing system: costs: wages and salaries $ 320,000 depreciation 160,000 utilities 240,000 total $ 720,000 distribution of resource consumption: activity cost pools assembly setting up other total wages and salaries 50% 40% 10% 100% depreciation 10% 55% 35% 100% utilities 15% 50% 35% 100% how much cost, in total, would be allocated in the first-stage allocation to the assembly activity cost pool? group of answer choices $212,000 $176,000 $196,000 $160,000