a construction company is taking bids on a project. companies' bids must estimate how long the project will take as there is a penalty for finishing late. one potential contractor determines that the average time to complete a project of this type is 40 weeks, has a standard deviation of 5 weeks, and is normally distributed. if the potential contractor wants just a five percent chance of finishing late, what should the due date be set to in weeks?