afety products currently outsources an electrical switch that is a component in its sprinkler systems. the switches are purchased for $35 each. the company is considering making the switches internally and has conducted a study to determine the costs involved. the costs below are projected annual production costs: unit-level material cost $ 7 unit-level labor cost $ 6 unit-level overhead $ 5 batch-level cost (8,000 units per batch) $ 30,000 product-level supervisory salaries $ 50,000 allocated facility-level costs $ 45,000 assume that the company needs 16,000 of the switches, which would be produced in two batches. assume also that the company will still be operating within the relevant range. if safety decides to make the parts under these conditions, the total relevant costs will be: