Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed on two machines M1 & M2 in that order.
Jobs M1 M2
A 13 21
B 8 16
C 30 25
D 11 27
E 15 25
For the sequence using Johnson’s Rule, the Make span = X