The project sponsor requires a project team composed of resources that live in four different time zones, working in four different locations. The project sponsor did not consider the implications of this requirement, and believes that the dispersion will provide an ideal project team that will save costs.
Where should this documented in the project charter?
A. As part of high-level requirements
B. In the key stakeholder list
C. In the overall project risks
D. As part of the resource management plan