A new segment of freeway is being built to connect two existing parallel freeway facilities. The
following traffic and roadway characteristics are expected:
Traffic Characteristics
• AADT = 85000 veh/day
• K = 12%
• D = 56%
• PHF = 0. 92
• 4% single-unit trucks
• 4% tractor-trailer trucks
Roadway Characteristics
• Grade in peak direction: 1. 5 miles, 2. 5 percent
• Total ramp density = 1. 75 per mile
• Lane widths = 11 ft
• Shoulder widths = 6 ft
a) Determine the number lanes necessary to ensure that this new freeway segment will operate at
no worse than LOS D during the peak hour in the peak direction.
b) How much additional traffic, in the peak direction, can be accommodated before the freeway
reaches capacity?