Given the above VSM, under the following operating
conditions:
Hours per shift: 8
Break minutes per shift: 30
Break Number per Shift: 2
Shifts per day: 3
Days per week: 5
Weekly Demand = 10,500 units
Annual Production Plan Metallservice Weekly Recieving Milling 5 Days C/T = 2 min C/O = 60 min Uptime = 74% 5 days 10 days 2 min. Note: C/T = Cycle Time; C/0= Changeover Time Weekly Delivery Schedule W