(a) You are asked to audit a project on Patient Life Cycle Management in a reputed hospital. How will you conduct the audit and what data you would like to collect during the audit process? (3) 27 (b) For an Electric Vehicle training program in an automotive industry, for the week 10, calculate the cost and schedule variances. Also calculate the CPI, SPI, CSI, ETC and EAC. Assume 50-50 rule for preparing the baseline budget: 202 ASSUN (6) Activity Predecessor Duration Actual Cost % complete (weeks) m($) A 4 500 100 B A 3 400 100 C A 6 1000 100 B 5 20 3 0 D E Budget ($) 400 600 800 1000 1200