Question 5, Problem 15.18 Homework: Chapter 15 Homework Part 1 of 36 Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is Sequence Job RG-05 sx1 BR-02 CX-01 DE-06 HW Score: 50.86%, 10.17 of 20 points O Points: 0 of 4 Save The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine conter has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Due Date Job BR-02 Date Job Received 230 Duration (days) 320 35 CX-01 235 360 40 DE-06 231 310 30 RG-05 228 300 15 SY-111 225 270 25 COCC