Assignment Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. Activity Immediate Time Estimates (In weeks) predecessor(s) Optimistic(a) Most Pessimistic likely (m) (b) A 4 8 10 B A 2 18 24 C A 8 12 16 D A 4 6 10 E B 1 2 3 F E,C 6 8 20 G E,C 3 4 H F 2 2 I F 6 6 J D.G.H 6 12 K 2 2 3 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated times, what is the critical path? 3. What is the estimated time of the critical path? 4. What is the activity variance along the critical path? 5. What is the probability of completion of the project before a week 46? 12 12 6 14