In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: 9 Activity Immediate Predecessor(s) Time (days) A 3 B A 4 C A 6 D B E B F C G D H E, F Carl's team should be able to complete the project in days. 6 4 4 6 8