Schedule acceleration provides assignment of costs of costs incurred to complete a project ahead of schedule. In general, if the owner requires the contractor to accelerate the schedule, who is responsible for all associated costs?
1) Owner
2) Contractor
3) Both the owner and contractor
4) None of the above