All of the following items should be considered in determining the capacity of a sprint but one. Which one should not be considered? Select one:
a. Capacity to work on product backlog items during the sprint
b. Other nonÂsprint commitments such as support, maintenance, working on other projects
c. Buffer
d. Other Sprint planning activities such as sprint planning, sprint review, sprint retrospective, and product backlog grooming
e. Sprint buffer
f. Personal time off
g. Project management activities