You have been asked to calculate the cost performance index for a project using earned value management techniques. It is currently day 18 of the project. Which of the following summarizes the current state of the project?
a) The project is ahead of schedule and under budget.
b) The project is behind schedule and under budget.
c) The project is ahead of schedule and over budget.
d) The project is behind schedule and over budget.