How should the complaint about the outcome of the project's first sprint be addressed?
1) Add the complaint to the product backlog to be addressed in the next sprint
2) Invite a member of the operations team to be part of the validation and sprint meetings
3) Ask the operations director to define the acceptance criteria to make clear the delivery is correct
4) Request that the issue be included in the next board of directors meeting to explain all of the needs