You are the project manager of the CCC Project. Stacy, a project team member, is confused about the statistical basis of a 3 sigma level of quality. You tell her that it has a ________________ percent degree of correctness. Select one:
1. 68.26
2. 99.73
3. 99.23
4. 99.99