Q 12 question 12 a project manager must publish a project schedule. activities, start/end times, and resources are identified. what should the project manager do next?

Respuesta :

The next step after publishing a project schedule activities, start/end times and resources are identified is TO CONFIRM THE AVAILABILITY OF RESOURCES

Once the resources are identified the project manager should make sure that the identified resources are available