EASY POINTS! What is the subtotal for the building materials in the bill? The subtotal should be the cost of the materials only. Don't add taxes or subtract any discounts.

A. $1,358.00
B. $1,658.00
C. $639.00
D. $239.69

EASY POINTS What is the subtotal for the building materials in the bill The subtotal should be the cost of the materials only Dont add taxes or subtract any dis class=

Respuesta :

Answer:

D. :)

Step-by-step explanation:

The total cost of materials is $1658

How to find the total cost?

Total cost is defined as the addition of the cost of individual material.

Cost of material=Cost*Number of pieces

Cost of:

  1. Lumber= 20*16.69
  2. Material A=2*20.78
  3. Material B=2*15.58
  4. Material C=6*21.38
  5. Material D=118*6.60
  6. Brick=500*0.22
  7. Pipe=10*8.44
  8. Hammer drill=1*150

Adding them up: 20*16.69+2*20.78+2*15.58+6*21.38+118*6.60+500*0.22+10*8.44+1*150

=$1658

Therefore, The subtotal of costs of material is $1658.

To know more about cost and materials refer:https://brainly.com/question/6857588

#SPJ2