Respuesta :
Answer:
the actual hours were 229,866
Explanation:
[tex]\frac{Cost\: Of \:Manufacturing \:Overhead}{Cost \:Driver}= Overhead \:Rate[/tex]
the predetermined overhead rate will be the quotient between the expected overhead and the expected value of the cost driver.
880,600 / 200,000 = 4.403
If we allocated 1,012,100
then actual hours x 4.403 = 1,012,100
actual hours = 1,012,100 / 4.403 = 229.866,000
the actual hours were 229,866
Answer:
The number of actual direct hours​ worked is $229,866 hours
Explanation:
In this question, first, we have to compute the predetermined overhead rate which is shown below:
Predetermined overhead rate = (Estimated manufacturing overhead costs) Ă· (Estimated direct labor hours)
= $880,600 Ă· $200,000
= $4.403
Now the number of actual direct hours​ worked equals to
= Â (Allocated manufacturing overhead) Ă· (Predetermined overhead rate)
= Â ($1,012,100) Ă· ($4.403)
= $229,866 hours