A 16\dfrac1216 2 1 ? 16, start fraction, 1, divided by, 2, end fraction kilometer stretch of road needs repairs. Workers can repair 2\dfrac142 4 1 ? 2, start fraction, 1, divided by, 4, end fraction kilometer of road per week. How many weeks will it take to repair this stretch of road?

Respuesta :

Answer: It will take [tex]7\dfrac{1}{3}[/tex] weeks to repair this stretch of road.

Step-by-step explanation:

Since we have given that

Part of road needs repair = [tex]16\dfrac{1}{2}=\dfrac{33}{2}[/tex]

Part of road worker can repair per week = [tex]2\dfrac{1}{4}=\dfrac{9}{4}[/tex]

We need to find the number of weeks that it will take to repair this stretch of road.

So, Number of weeks is given by

[tex]\dfrac{33}{2}\div \dfrac{9}{4}\\\\=\dfrac{33}{2}\times \dfrac{4}{9}\\\\=\dfrac{66}{9}\\\\=\dfrac{22}{3}\\\\=7\dfrac{1}{3}[/tex]

Hence, it will take [tex]7\dfrac{1}{3}[/tex] weeks to repair this stretch of road.

Answer:

[tex]7\frac{1}{3}\text{ weeks}[/tex]

Step-by-step explanation:

Given,

Total distance have to stretch = [tex]16\frac{1}{2}[/tex] km,

Also, the distance repaired by workers each week = [tex]2\frac{1}{4}[/tex] km,

Thus, the number of weeks required to repair whole distance

[tex]=\frac{\text{Total distance have to stretch}}{\text{Distance repaired in one week}}[/tex]

[tex]=\frac{16\frac{1}{2}}{2\frac{1}{4}}[/tex]

[tex]=\frac{\frac{33}{2}}{\frac{9}{4}}[/tex]

[tex]=\frac{66}{9}[/tex]

[tex]=7\frac{1}{3}[/tex]