During 2013, Tanner Manufacturing expected Job No. 26 to cost $300,000 of overhead, $500,000 of materials, and $200,000 in labor. Tanner applied overhead based on direct labor cost. Actual production required an overhead cost of $280,000, $550,000 in materials used, and $210,000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?

Select one:

a. $1,000,000

b. $1,040,000

c. $1,060,000

d. $1,075,000