This document summarizes why the project is important by describing the benefits of a selected component, and is used as a basis for authorizing further project management activities:_______.a. program management planb. business casec. SWOT analysisd. guiding principle

Respuesta :

Answer:

B. Business Case

Explanation:

The program management plan is a document that updates the progress of any project. So, option A is wrong.

SWOT analysis provides the internal and external strengths and opportunities of any corporation. So, this is also incorrect.

The guiding principle gives a company to adhere to the rules and responsibilities. Therefore, it is not correct.

The business case summarizes the project by describing the benefits of a selected component. It also emphasizes to initiate a project. So, it is the right answer.