Answer:total cost for Assembly department is 131,220 and for finishing department is 85,240 and the factory overheads for assembly and finishind department respectively is 61,120 and 38,240
Explanation:
WEBER COMPANY
Production costs per department
Assembly Finishing total
raw material $31,900 $23,100 $55,000
labour cost $38,200 $23,900 $62,100
factory overheads $61,120 $38,240 $99,360
total cost $131,220 $85,240 $216,460
to calculate the factory overheads we take the amount for labour in a department and multiple it by 160% meaning for Assembly department it is 38200*160/100= 61120