Respuesta :
30 men -> 40 days
1 man -> 1/1/3 days
30-5men = 25 men
25 men -> 1/1/3 x 25
= 33/1/3 days
1 man -> 1/1/3 days
30-5men = 25 men
25 men -> 1/1/3 x 25
= 33/1/3 days
Answer: 48 days
Step-by-step explanation:
If it takes 30men 40days to complete a task, 1 man takes 30×40= 1200 days
25 men will therefore take 1200/25= 48 days.