What is the potential downside to bringing project workers into a project too early? a. People don't like being told what to do, but are usually enthusiastic if they can participate in creating the project plan. b. When the people who perform the work help to plan it, many more details may be considered. c. Bringing SMEs on board before they are needed to complete the project could be expensive.

Respuesta :

Answer:

Option B

Explanation:

Down slide means "Fall" of something , so reframing the question , what is the potential fall to bringing project workers on work too early ?

The fall here is when people who are going to perform the work are part of the planning process for the early stage ,more areas could be covered , because they are the ones doing the project and it gives an avenue for them to give suggestions and contribution and a way forward in the project.