Respuesta :
Answer: True
The control chart is graph,that is used to study how a process changes over time with date plotted in time order.
Control charts are a valuable tool for monitoring process performance. However, you have to be able to interpret the control chart for it to be of any value to you.
A control chart can use to measure schedule Trends.
Step-by-step explanation: in the situation where schedule changes control chart can be use to monitor the process.
The control chart can also serve as guide that helps to notify in case of changes.
The statement stating for a more complex project, statistical analysis can be applied to a Control Chart to identify potential causes of schedule deviation is true.
A control chart can be given as the graphical representation of the change in process concerning time. Since there has been the measurement of the value with the daily monitoring, the charts have been used for the measurement of the trends in the data.
The application of a complex chart has been in the statistical data as well, which has been applied for the identity of the cause of schedule deviation. Thus, the statement has been true.
For more information about the control chart, refer to the link: