PERT analysis computes the variance of the total project completion time as A. the sum of the variances of all activities not on the critical path. B. the variance of the final activity of the project. C. the sum of the variances of all activities on the critical path. D. the sum of the variances of all activities in the project.

Respuesta :

Answer:

C. the sum of the variances of all activities on the critical path.

Step-by-step explanation:

PERT is an acronym for Program Evaluation and Review Technique. PERT analysis is for task examination scheduling and determination of a variation of the Critical Path Method method. It aims to control cost ND time by analyzing the required time to complete a given task and other related factors.

A PERT chart consists of circles or rectangles which depicts the various milestones of project.