Which of the follow top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project? A. ApportionB. Function pointC. Phase estimatingD. Learning curveE. Consensus

Respuesta :

Answer:

Apportion

Explanation:

Apportionment method is also known as analogous estimating, uses historical data of past projects that are relatively standard to allocate duration and costs to various segments of the current project.

This is performed by assigning percentages of the total planned duration or costs to each segment .