If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are 1,600 units at $13, the direct materials quantity variance is $5,200 favorable.

Respuesta :

Answer:

The answer is FALSE

Step-by-step explanation:

Materials quantity variance = (SQ -AQ) * SP

                                             = (2,000 - 1,600)* 12

                                              $4800 Favourable