Answer:
The delivery cycle time was 26.9
Explanation:
The delivery cycle time is computed as:
Delivery cycle time = Wait time + Throughput time
where
Wait time is 13.6
The formula for computing the throughput time is as:
Throughput time = Move time + Process time + Queue time + Inspection time
where
Move time is 3.3
Process time is 2.7
Queue time is 7.0
Inspection time is 0.3
Putting values above:
Throughput time = 3.3 + 2.7 + 7.0 + 0.3
Throughput time = 13.3
Now, putting both the values above:
Delivery cycle time = 13.6 + 13.3
Delivery cycle time = 26.9