Solution and explanantion
To record the assignment of overhead to the assembly and finishing department, debit the work in process assembly department, debit the work in process finishing department and credit manufacturing overhead as below:
date Particulars                         Debit Credit
Work in process – assembly department 71040 Â
Work in process – finishing department 29440 Â
Manufacturing department                       100480 Â
Working note:
Labor cost assigned to assembly = $44400
Labor cost assigned to finishing = $62800 minus 44400 = $18400
Manufacturing overhead assigned to assembly =[tex]=\$ 44400 * 160 \%=\$ 71040[/tex]
Manufacturing overhead assigned to fiishing =[tex]\$ 18400 * 160 \%=\$ 29440[/tex]