Answer:
No; The IRR is less than the required return.
Explanation:
Calculation  of IRR is given by the formula: Lr x NPVL / NPVL - NPVH x (Hr - Lr)
where
Lr  = Lower rate of discount
Hr = Higher rate of discount
NPVH = NPV at Higher discount rate
NPVL = NPV at Lower discount rate
Assume a low discount rate of 1% and a high rate of 20%
NPV at 1%
Particulars     Year 0  Year 1   Year 2  Year 3
Cash flows    152,000  71,800  86,900  (11,200)
DCF 1% Â Â Â Â Â Â Â Â 1 Â Â Â Â Â 0.99 Â Â 0.98 Â Â Â 0.97
Present values (152,000) 71,082 85,162 Â (10,864)
NPV = $6,620
NPV at 20%
Particulars     Year 0  Year 1   Year 2  Year 3
Cash flows    152,000  71,800  86,900  (11,200)
DCF 20% Â Â Â Â Â Â Â Â 1 Â Â Â Â Â 0.83 Â Â 0.69 Â Â Â 0.58
Present values (152,000) 59,594 59,961 Â (6,496)
NPV = ($38,941)
Substituting values in the IRR formula we have:
1% x [($6,620 / ($6620 - (38,941))] x (20% - 1%) = 2.06%
Therefore we reject the project because it gives an IRR lower than the required rate of return of 15.5%