Respuesta :
Answer:
The correct answer is C.
Explanation:
Giving the following information:
Pinnacle Corp. budgeted $700,000 of overhead costs for the current year.
Pinnacle's plantwide allocation base, machine hours, was budgeted at 100,000 hours.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 700,000/100,000= $7 per machine-hour.
Answer:C. $7.00 per machine-hour
Explanation:
PLANT-WIDE FACTORY OVERHEAD RATE = Predetermined overhead cost ÷ predetermined plantwide allocation base
Therefore, Required parameters to calculate plantwide factory overhead rate for the year.
Predetermined overhead cost for the year = $700,000
Predetermined plantwide allocation base (Machine-hours) = 100,000
PLANT-WIDE FACTORY OVERHEAD RATE = $700,000 ÷ 100,000 = $7
$7 PER MACHINE-HOUR