Answer:
Ending WIP= $17,000
Explanation:
Giving the following information:
The cost of the beginning work in process inventory is $70,000
The costs of goods manufactured is $935,000
Direct materials cost is $339,000
Direct labor cost is $219,000
Allocated overhead cost is $324,000
Using the following formula, we can calculate the ending work in process:
cost of goods manufactured= beginning WIP + direct materials + direct labor + allocated manufacturing overhead - Ending WIP
935,000= 70,000 + 339,000 + 219,000 + 324,000 - Ending WIP
Ending WIP= $17,000