Bisutti Cams is producing its Racing Camshaft models RC1 and RC2. It is a three-state process that involves collecting the appropriate items from inventory, assembling, and then inspecting them. Bisutti Cams is making its labor estimates for the next four quarters for the collecting, assembling and inspecting operations. The RC1 requires 5 hours of labor and the RC2 requires 2 hours. The collecting process uses 20% of its labor resources, the assembling uses 70%, and the inspecting uses 10%. The production schedule for the next four quarters is given below.

Calculate the labor hours required in the collecting, assembling, and inspecting processes for the next four quarters.

Quarter
Endproduct 1 2 3 4
RC I 100 120 200 140
RC 2 200 250 150 100

Respuesta :

Answer:

Bisutti Cams

The total Hours for collecting, assembling, and inspecting processes for the next four quarters for the two products are as follows.

Labor Hours required in the Four Quarters  RC1

 Collecting, 20% Assembling, 70%   Inspecting processes 10%  

Quarter 1     100                       350                            50

Quarter 2     120                       420                          60

Quarter 3     200                     700                          100

Quarter 4     140                        490                        70                          

Total Hrs.  560                     1960                         280                        

Labor Hours required in the Four Quarters  RC2

   Collecting, 20% Assembling, 70%   Inspecting processes 10%  

Quarter 1     80                       280                            40

Quarter 2      100                     350                         50

Quarter 3      60                        210                          30

Quarter 4      40                           140                        20                      

Total Hrs   280                        980                         140                      

Explanation:

Labor Hours required in the Four Quarters

Quarter

Endproduct                             1           2         3             4

RC I                                         100       120     200        140

No of Hours Required             5          5         5             5    

Total Hours Required         500        600     1000      700

Step 1 ) We multiply  number of hours with  the products in each quarter to get the total hours required.

RC 2                                             200        250        150          100

No of Hours Required                   2            2            2             2    

Total Hours Required For R2     400          500      300       200

     

Step 2) We find the collecting, assembling, and inspecting hours by applying the percentages to each quarter hour.

Labor Hours required in the First Quarter

                                              RC1                    RC2

Collecting, 20%                      100                    80

Assembling, 70%                  350                   280

Inspecting processes 10%     50                    40          

First Quarter                         500                   400            

Labor Hours required in the Second Quarter

                                              RC1                    RC2

Collecting, 20%                     120                    100

Assembling, 70%                   420                    350

Inspecting processes 10%      60                      50          

Second Quarter                         600                  500          

Labor Hours required in the Third Quarter

                                                RC1                    RC2

Collecting, 20%                      200                      60

Assembling, 70%                    700                      210

Inspecting processes 10%        100                      30          

Third  Quarter                            1000                   300          

Labor Hours required in the Fourth Quarter

                                                    RC1                    RC2

Collecting, 20%                         140                      40

Assembling, 70%                        490                    140

Inspecting processes 10%          70                      20          

Fourth  Quarter                            700                   200