Answer:
The NPV of the machine is closest to -$34.48
Explanation:
The net present value (NPV) of the project is the present value of the future net cash flows expected from the project less the initial cost of the project. The cash inflows from this project are the cost savings that are in a form of annuity and an amount for salvage value receivable at end of year 6. Thus, the NPV of the project is,
NPV = 4000 * [ (1 - (1+0.12)^-6) / 0.12 ] + 3000 / (1+0.12)^6 - 18000
NPV = - $34.48
Answer:
$-34.77
Explanation:
The net present value is the present value of after tax cash flows from an investment less the amount invested.
NPV can be calculated using a financial calculator:
Cash flow in year 0 = $-18,000
Cash flow each year from year 1 to 5 = $4,000
Cash flow in year 6 = $4,000 + $3,000 = $7,000
I = 12%
NPV = $-34.77
To find the NPV using a financial calacutor:
1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.
2. After inputting all the cash flows, press the NPV button, input the value for I, press enter and the arrow facing a downward direction.
3. Press compute
I hope my answer helps you