Respuesta :
Answer:
$109.80 per unit
Explanation:
For we to be able to calculate the or solve the problem, we are to use the following method
Firstly
Variable cost per unit = $728,190 ÷ 8,700 units
Variable cost per unit = $83.70 per unit
Secondly
Fixed cost per unit at 8,900 units = $232,290 ÷ 8,900 units
Fixed cost per unit = $26.10 per unit
Lastly
Total cost = Variable cost + Fixed cost
Which we have as;
Total cost = $83.70 per unit + $26.10 per unit
Total cost = $109.80 per unit
Answer:
Total cost = $977,220
Explanation:
Variable cost.
They vary with volume of activity
Variable cost per machine hour = Total variable cost/machine hours
VC per machine hour = 728,190 /8700= $83.7 per machine hour
Fixed cost of maintenance
The fixed costs are cost that remain the same within an activity. The don't vary with volume withing an activity range.
Fixed costs =$232,290.
Total cost at 8,900 hours
= variable cost + fixed cost
= ($83.7  × 8900)  + $232,290.
Total cost = $977,220