Answer:
labour rate variance  = $616 unfavorable
Explanation:
The rate variance would be the difference between the standard labour cost of the 500 actual hours worked  and the actual labour cost.
This derived below:
                                       $
Standard labor cost ($23 per × 500)  =     11500
Actual labour cost                       (12,116)
labour rate variance                   $616 unfavorable