Answer:manufacturing cycle efficiency (MCE)= 0.40
Explanation:
Solution to solve for the manufacturing cycle efficiency (MCE)
Manufacturing Cycle Efficiency (MCE) is solved using the following
Throughput time = Process time + Inspection time + Move time + Queue time
= 6 Days + 0.6 Days + 0.4 Days + 8 Days
= 15 Days
Therefore, the Manufacturing cycle efficiency (MCE) = Process time / Throughput time
= 6 Days / 15 Days
= 0.40
Therefore, the Manufacturing Cycle Efficiency (MCE) will be 0.40