Answer:
NPV of Project at 5% WACC = 7.71
Explanation:
Cash flow at year 0 = -27
Cash flow at year 1 = 13
Cash flow at year 2 = 17
Cash flow at year 3 = 8
WACC = 5%
NPV of Project A at 5% WACC = -27 + 13/ (1.05) + 17/(1.05)2 + 8/(1.05)3