A construction crew has just built a new road. They built the road at a rate of 7 kilometers per week. They built 8.75 kilometers of road. How many weeks did it take them?

Respuesta :

Answer:

1.25

Step-by-step explanation:

Total Built/Rate of Building

8.75/7=1.25

It took 1.25 weeks.