Answer:
$239,300
Explanation:
As per the data given in the question,
Activity         Cost driver   Amount  M     XY     Total
Production setup No. of setups $79,000 16 Â Â Â Â 24 Â Â Â Â 40
Material handling No. of parts  $58,000 64    16      80
Packaging cost No. of units    $300,500  $105,000  $70,000 $175,000
                         $437,500
Allocation of Product XY :
Production setup $79,000 ÷ 40 × 24             $47,400
Material handling $58,000 ÷ 80 × 16             $11,600
Packaging cost $300,500 ÷ $175,000 × $105,000 $180,300
Total overhead                              $239,300
We simply added the production setup, material handling and packaging cost