Answer:
$10,241.53
Explanation:
Using the activity-based costing system, Overhead cost for Product K91B would be?
Setting up batches 89 batches x $59.56= Â Â Â Â Â Â Â Â Â $5300.84
Processing customer orders 39 orders x $72.96= Â Â Â $2,845.44
Assembling products 493 hours x $4.25= Â Â Â Â Â Â Â Â Â $2,095.25
Total Overhead cost                            $10,241.53