You can make small 20 small frames in 4 days or 21 large frames in 3 days. A customer has just place a order with you for 40 small frames and 64 large ones. Approximately how many days will it take you to make them all ?

Respuesta :

Answer:

I got 17.

Step-by-step explanation:

Because it takes 4 days to make 20 small frames, it takes 8 days to make 40. And because it takes 3 days to make 21 frames, and 21 multiplied by 3 is 63 (one less than 64), it would take 9 days (3 times the amount for 21) to make 64 large frames. In all, it would take APPROXIMATELY 17 days (9 +8 is 17)