SciTech needs to hire an engineer to develop a prototype for a project. The company asks each engineer to provide a cost and time estimate for the work. Each bid is shown in the table.


Which engineer would be the most cost-effective for the project?

Camilla
John
Nora
Oracio

Respuesta :

Answer:

Oracio

Explanation:

Mutiply the cost per hour by the time to complete the job

Camila 40x20=800

John 30x30= 900

Nora 20x40=800

Oracio 15x50=750

The Oracio engineer would be the most cost-effective for the project.

  • The calculation is as follows:

Here we Mutiply the cost per hour by the time to complete the job

So,

Camila 40(20)=800

John 30(30)= 900

Nora 20(40)=800

Oracio 15(50)=750