Answer:
Total cost= $6,267
Explanation:
Giving the following information:
Direct Materials $3,405
Direct Labor Hours 50 labor hours
Direct Labor wage rate $13 per labor hour
Machine Hours 158
The predetermined overhead rate is $14 per machine-hour.
To calculate the total cost, we need to use the following formula:
Total cost= direct material + direct labor + allocated overhead
Total cost= 3,405 + 13*50 + 14*158
Total cost= $6,267