Answer:
3 days would take the 15 workers to finish the same task
Step-by-step explanation:
Let us use this relation to solve the question
∵ 5 workers can complete a certain task in 9 days
∴ N = 5 workers and T = 9 days
→ By using the relation above
∴ 5 × 9 = k ⇒ (1)
∵ If there are 15 workers will make the same task
∵ They can finish it in x days
∴ N = 15 workers and T = x days
→ By using the relation above
∴ 15 × x = k ⇒ (2)
∵ k is the same task, then equate the left sides of (1) and (2)
∴ 15 × x = 5 × 9
∴ 15x = 45
→ Divide both sides by 15 to find x
∴ x = 3 days
∴ 3 days would take the 15 workers to finish the same task