Respuesta :
Answer:
cumulative learning factor for 85% and 400 units = 127.6
cumulative learning factor for 90% and 400 units = 189.3
total labor costs for producing the next 350 units = labor cost for producing 400 units - labor cost for producing 50 units
85% learning curve:
total labor costs for producing 400 units = $1,000 x 127.6 = $127,600
total labor costs for producing 50 units = $1,000 x 50 = $50,000
total labor costs for producing the next 350 units = $127,600 - $50,000 = $77,600
labor cost per unit = $77,600 / 350 = $221.71
90% learning curve:
total labor costs for producing 400 units = $1,000 x 189.3 = $189,300
total labor costs for producing 50 units = $1,000 x 50 = $50,000
total labor costs for producing the next 350 units = $189,300 - $50,000 = $139,300
labor cost per unit = $139,300 / 350 = $398

Answer:
94.72
Explanation:
given data
time taken = 15 min
learning curve = 80%
solution
we use here formula for this task that is
T(n) = T × .............1
here T(n) is time taken for n unit and T is time for 1st hour and No is no of time and b is slope leaning
put here value for 25 we get
T(n) = 15 ×
b(25) = 0.355
as leaning curve coefficient table
as here with 80% leaning curve
unit timer coefficient = 0.355
so T(25) = 15 × 0.355
T(25) = 5.325 min
and
for 10 exam
leaning curve 80% co efficient is 6.315 from table
so T (10) = 15 × 6.315
T (10) = 94.72 min