Respuesta :
Answer:
Explanation:
The Earned Value Analysis for each term can be computed as follows:
Term                  Acronym         Formula       Value
Budget At Completion  BAC         =1000×500        500,000
Planned Value          PV          =400×500         200,000
Earned Value           EV          =500000×0.45     225,000
Actual Cost            AC                             250,000
Cost Variance         CV            [tex]=EV - AC[/tex]         -25,000
Schedule Variance     SV           [tex]=EV - PV[/tex]           25,000
Cost Performance Index CPI Â Â Â Â Â Â Â Â Â Â [tex]=EV / AC[/tex] Â Â Â Â Â Â Â Â Â Â Â Â 0.9
Schedule Performance Index SPI Â Â Â Â Â [tex]=EV / PV[/tex] Â Â Â Â Â Â Â Â Â Â Â 1.125
Estimate At Completion EAC Â Â Â Â Â Â Â Â [tex]=BAC / CPI[/tex] Â Â Â Â Â Â Â 555,556
Estimate To Complete  ETC         [tex]=EAC - AC[/tex]        305,556
Variance At Completion VAC Â Â Â Â Â Â Â Â [tex]=BAC - EAC[/tex] Â Â Â Â Â Â Â -55,556