contestada

Suppose a company has a contract to construct a building for a total sales price of $60 million. The building will take an estimated three years to complete, with a total estimated cost of $50 million. If the company incurs costs of $20 million in Year 2, how much revenue and profit should be recognized in Year 2 if the percentage of completion method is used